Denham

DENHAM

BATTERY ENERGY STORAGE SYSTEM (BESS)

Our live online event is live from 4pm – 7pm on 6th May 2025. Use live chat at the bottom right of the screen.

WHO IS THE APPLICANT?

  • Voltwise Power Holdings Limited – An organisation dedicated to becoming one of the leading utility-scale battery energy storage owners and operators across Europe.
  • First launched in the UK and Germany, with a mission to provide intelligent, safe and reliable BESS across Europe.
  • Dedicated to delivering net zero emissions targets.

WHY IS BATTERY STORAGE IMPORTANT

  • Battery energy storage is crucial for the UK’s transition to a clean energy future and is vital for achieving its net-zero targets. It helps stabilise the grid, integrate renewable energy sources, and will help to reduce costs.
  • England is aiming to achieve net-zero by 2050.
  • By 2050, according to NESO, we may require up to 40GW of energy storage.
  • The British Energy Security Strategy set ambitions for 30GW of energy storage across the UK by 2030.

LOCATION

  • The application site is located on land at Pinstone Farm, Oxford Road, Gerrards Cross, SL9 7AL.
  • The development will connect to Denham Substation via underground cable.
  • There is available grid capacity at this location.
  • There are very few suitable locations in the country such as this.
  • This location minimises the amount of connection infrastructure required which is better for the environment and means lower embodied carbon emissions.
  • The proposed site is approximately 0.6 hectares (1.5 acres).

SITE LAYOUT

  • Containerised battery storage facility (30 x containers) with up to 60MW of energy storage.
  • Circa 6.5-metre-long containers at a height of approx. 2.5 metres and 132kV substation.
  • An access track, electricity meter building, fences, and containers housing batteries and related equipment would make up the development.
  • The existing hedgerows and trees will be preserved, and a belt of new planting and other native trees and plants is proposed to fully screen the development.
  • Stores surplus electricity – returns electricity to the grid to meet demand helping to lower carbon emissions.
  • This balances the grid’s supply and demand.

SITE ELEVATIONS

  • Indicative Transformer Elevations at a height of approx. 7.4 metres.
  • Circa 6.5 metre-long containers at a height of approx. 2.5 metres.
  • Containerised battery storage facility (30 x containers) with up to 60MW of energy storage.
  • 132kV Substation-Indicative DNO Compound Elevations.

Download the
Presentation

PUBLIC CONSULTATION BOARD DENAHM.pdf

PAN Questionnaire

DENHAM

BATTERY ENERGY STORAGE SYSTEM (BESS)







YesNo